We have started the implementation of our biggest challenge for 2010 year- the production and erection of a complete automatic welding line for manufacturing membrane panels.
The machine consists of a complete transportation system , that automatically passes the components (pipes- diameter 60-120mm) of 24 meter length, and flat bars ( 24 meters length ) that connect them.
Firs the elements are calibrated on two machines and passed to the blasting machine, and finally ends at the pipe but welding station. The greatest advantage of this production line is the fact that it is able to adjust it to mass production or single unit production with a possibility to implement rapid changes. Everything is computer controlled.
We have decided to use in this project welding machines offered by ESAB company, which with we have partnered. Additionally there can be use a laser welder that has been ordered by the customer.
The complete facility is manufactured in a new building and is an innovative project, made from the beginning by our Design Office that cooperated ideally with the customers technicians.
What is most important- the facility must be constructed in 5 months- there is no other way, We must do it in time!